文章來源:中(zhong)國葛洲壩集團(tuan)公司(si) 發布時(shi)間:2010-10-21
近日,由葛洲壩集團五公司承建的國電集團內蒙古武川西烏蘭不浪紅山風電一期工程33臺風機基礎全部澆筑完成,比合同工期提前21天。
該(gai)工(gong)(gong)程(cheng)位于內蒙古自(zi)治區呼和浩特市武川縣。由葛洲壩集團五公司(si)承建的風(feng)機基礎土建工(gong)(gong)程(cheng)合同(tong)工(gong)(gong)期(qi)(qi)(qi)為(wei)2009年8月(yue)1日(ri)至2009年11月(yue)1日(ri)。由于受氣候限制,十月(yue)下(xia)(xia)旬(xun)后將(jiang)不(bu)再具備大(da)體積混凝(ning)土施工(gong)(gong)條件,為(wei)保(bao)證工(gong)(gong)程(cheng)務期(qi)(qi)(qi)必成(cheng),項(xiang)目部(bu)在停電(dian)、缺水、等(deng)不(bu)利(li)條件下(xia)(xia),科學(xue)組織、精(jing)心施工(gong)(gong)、日(ri)夜奮戰,最終保(bao)證了節點工(gong)(gong)期(qi)(qi)(qi),是(shi)該(gai)工(gong)(gong)程(cheng)五個參(can)建單(dan)位中唯一一個按期(qi)(qi)(qi)完(wan)成(cheng)施工(gong)(gong)任務的單(dan)位,受到了業主和監理單(dan)位的高(gao)度贊譽。