文章來源:中國石油天然氣集團公(gong)司 發布時(shi)間:2010-09-15
經過72小時(shi)雨(yu)中(zhong)(zhong)激戰,陜京(jing)二(er)(er)(er)線(xian)增輸(shu)工程(cheng)動火作(zuo)業(ye)于(yu)9月10日(ri)20時(shi)順利(li)完成(cheng)。這次中(zhong)(zhong)國石(shi)油(you)天然氣(qi)管(guan)(guan)道(dao)建(jian)設史上最(zui)大(da)的(de)一(yi)次動火作(zuo)業(ye)完成(cheng)后,陜京(jing)二(er)(er)(er)線(xian)的(de)年輸(shu)量將從120億立(li)方米增加到170億立(li)方米,不(bu)僅可(ke)進(jin)一(yi)步(bu)提高向京(jing)、津(jin)及(ji)周邊地區平穩(wen)供氣(qi)的(de)安全系數,而且為即將投產的(de)中(zhong)(zhong)亞輸(shu)氣(qi)管(guan)(guan)道(dao)、西氣(qi)東(dong)(dong)輸(shu)二(er)(er)(er)線(xian)進(jin)入華北(bei)和(he)東(dong)(dong)北(bei)地區市場打(da)開了通道(dao)。
此次動火作業是(shi)由北(bei)(bei)(bei)京(jing)油氣(qi)(qi)(qi)調控中(zhong)(zhong)(zhong)心、北(bei)(bei)(bei)京(jing)天然氣(qi)(qi)(qi)管道(dao)公司、塔里(li)(li)木(mu)油田(tian)、長(chang)慶油田(tian)、長(chang)北(bei)(bei)(bei)氣(qi)(qi)(qi)田(tian)、華北(bei)(bei)(bei)天然氣(qi)(qi)(qi)銷售、西(xi)氣(qi)(qi)(qi)東(dong)輸(shu)、中(zhong)(zhong)(zhong)石(shi)化等(deng)(deng)8個單(dan)位(wei)聯動完成的浩(hao)大(da)工程(cheng)。9月8日20時,北(bei)(bei)(bei)京(jing)油氣(qi)(qi)(qi)調控中(zhong)(zhong)(zhong)心下達指令,塔里(li)(li)木(mu)、長(chang)慶、長(chang)北(bei)(bei)(bei)和(he)中(zhong)(zhong)(zhong)石(shi)化等(deng)(deng)氣(qi)(qi)(qi)田(tian)停止向陜京(jing)二線(xian)輸(shu)氣(qi)(qi)(qi),西(xi)氣(qi)(qi)(qi)東(dong)輸(shu)、大(da)港儲氣(qi)(qi)(qi)庫等(deng)(deng)氣(qi)(qi)(qi)源地通(tong)過(guo)陜京(jing)一(yi)線(xian)開始向北(bei)(bei)(bei)京(jing)、天津等(deng)(deng)主要用(yong)戶供氣(qi)(qi)(qi),陜京(jing)二線(xian)榆林、興(xing)縣、陽(yang)曲和(he)石(shi)家莊壓氣(qi)(qi)(qi)站的54個動火聯頭(tou)作業點(dian)同時開工。來自(zi)北(bei)(bei)(bei)京(jing)天然氣(qi)(qi)(qi)管道(dao)公司、中(zhong)(zhong)(zhong)油一(yi)建、中(zhong)(zhong)(zhong)油六建、華北(bei)(bei)(bei)油建和(he)焊接檢驗、安全監理等(deng)(deng)單(dan)位(wei)立即進入(ru)現(xian)場,數(shu)十臺大(da)型車輛、數(shu)十套(tao)大(da)口徑三通(tong)、百余(yu)臺切割(ge)機(ji)和(he)電(dian)焊機(ji)一(yi)齊(qi)匯集在狹窄的坑(keng)道(dao)里(li)(li)展開作業,雨夜瞬(shun)間被照得(de)通(tong)明。
動火作業(ye)(ye)是指在(zai)已投入(ru)運營(ying)的輸氣(qi)管(guan)道(dao)上(shang)進行切割、吊裝、焊接施(shi)工(gong),是天(tian)然氣(qi)管(guan)道(dao)建設中難度最大的施(shi)工(gong)作業(ye)(ye)。因此,對用戶(hu)協調、施(shi)工(gong)準備(bei)、工(gong)種銜(xian)接、安(an)全保(bao)護和作業(ye)(ye)時間(jian)等方面的要求非常高。
從7日(ri)開(kai)始,陜(shan)京二(er)線經過的(de)省區普降中到大雨,讓時間(jian)緊、任務(wu)重(zhong)的(de)動(dong)火(huo)(huo)作業再添難度(du)。各施工單位嚴(yan)格雨中作業程序,各路(lu)技術高手克服(fu)泥濘濕滑帶來(lai)的(de)困(kun)難,按照施工設計要(yao)求,一絲不茍地完成關(guan)閉閥室、放空天然氣(qi)、氮(dan)氣(qi)置(zhi)換(huan)、可燃氣(qi)體(ti)分(fen)析檢測、動(dong)火(huo)(huo)點土(tu)方開(kai)挖、動(dong)火(huo)(huo)連頭處管(guan)(guan)道打孔(kong)、管(guan)(guan)道切割(ge)、管(guan)(guan)道安裝、對縫焊接、探傷檢測等16道工序。至10日(ri)20時,所(suo)有動(dong)火(huo)(huo)點都在規定時間(jian)內(nei)完成作業,陜(shan)京二(er)線按時恢復輸氣(qi)生產。