文章來源:中國(guo)華電集團公司 發布(bu)時間(jian):2010-05-20
5月16日上午9時16分,中國華電集團公司寧夏靈武發電有限公司二期兩臺100萬千瓦空冷機組工程三號鍋爐鋼架在鞭炮聲中緩緩起吊,安裝就位,較里程碑計劃提前82天,為機組早日投產和創“國優金獎”工程奠定了基礎。
該公司二期(qi)工(gong)(gong)(gong)程是(shi)世界首臺(tai)百萬千(qian)瓦空冷機組(zu),也是(shi)寧東能源(yuan)化工(gong)(gong)(gong)基地“一(yi)號(hao)工(gong)(gong)(gong)程”。自(zi)2008年12月(yue)27日(ri)(ri)“破土(tu)”動工(gong)(gong)(gong)以(yi)來,該公司克服時間緊、任務重、環境(jing)條件差、無施(shi)(shi)工(gong)(gong)(gong)經(jing)驗可借鑒等諸(zhu)多困難,充分發(fa)揮業(ye)主(zhu)單(dan)位在工(gong)(gong)(gong)程管(guan)(guan)理中的(de)(de)主(zhu)導作用,組(zu)織(zhi)參建各(ge)方超前(qian)謀劃,精(jing)心(xin)組(zu)織(zhi),認真(zhen)準備并落(luo)實(shi)各(ge)項施(shi)(shi)工(gong)(gong)(gong)措施(shi)(shi)方案,始(shi)終以(yi)“創國優金獎(jiang)”為(wei)目標,高(gao)起點、高(gao)標準,嚴格(ge)現(xian)場施(shi)(shi)工(gong)(gong)(gong)管(guan)(guan)理和(he)階段驗收(shou),規范各(ge)項工(gong)(gong)(gong)程管(guan)(guan)理程序,施(shi)(shi)工(gong)(gong)(gong)安全、質(zhi)(zhi)(zhi)量(liang)(liang)、工(gong)(gong)(gong)期(qi)、造價始(shi)終處于受控狀態(tai)。自(zi)3月(yue)16日(ri)(ri)三(san)號(hao)主(zhu)廠房(fang)和(he)鍋爐房(fang)順利實(shi)現(xian)澆筑第一(yi)方混凝土(tu),至5月(yue)16日(ri)(ri)實(shi)現(xian)三(san)號(hao)鍋爐鋼架(jia)的(de)(de)吊(diao)裝,土(tu)建專業(ye)在確(que)保澆注混凝土(tu)質(zhi)(zhi)(zhi)量(liang)(liang)的(de)(de)同時,精(jing)心(xin)組(zu)織(zhi),加(jia)班加(jia)點,合理調配施(shi)(shi)工(gong)(gong)(gong)機械、施(shi)(shi)工(gong)(gong)(gong)人員,在短(duan)短(duan)2個月(yue)的(de)(de)時間里(li),完成(cheng)了(le)鍋爐基礎13000多方混凝土(tu)的(de)(de)澆筑任務,為(wei)鋼架(jia)的(de)(de)吊(diao)裝爭(zheng)得了(le)時間,創造了(le)條件。與此(ci)同時,加(jia)大圖紙和(he)鋼架(jia)設備的(de)(de)催交力度,嚴把質(zhi)(zhi)(zhi)量(liang)(liang)驗收(shou)關(guan),從源(yuan)頭上控制(zhi)和(he)杜(du)絕了(le)鍋爐鋼架(jia)帶缺(que)陷(xian)吊(diao)裝。