文章來源:中國葛(ge)洲壩集團公司(si) 發布時(shi)間:2010-03-12
近日,由葛洲壩集團五公司承建(jian)(jian)的開(kai)封火電廠擴建(jian)(jian)工程(cheng)2號(hao)機(ji)組(zu)順利通過168小時滿負(fu)荷試運(yun)行,投(tou)產發(fa)電。至此,該工程(cheng)兩臺機(ji)組(zu)全部投(tou)產發(fa)電,創造(zao)了火電行業(ye)機(ji)組(zu)建(jian)(jian)設(she)投(tou)產新紀錄,獲得多方(fang)贊譽。
河南開封火電廠(chang)擴建(jian)工(gong)(gong)(gong)程(cheng)(cheng)位于(yu)開封京源發(fa)(fa)電有限責任公(gong)司老廠(chang)東(dong)部,葛(ge)洲(zhou)壩(ba)集團五(wu)公(gong)司承擔了該工(gong)(gong)(gong)程(cheng)(cheng)兩臺60萬千瓦超(chao)臨(lin)界機(ji)組的燃煤系統、燃油系統、除灰(hui)工(gong)(gong)(gong)程(cheng)(cheng)、附屬工(gong)(gong)(gong)程(cheng)(cheng)的建(jian)設任務(wu)。工(gong)(gong)(gong)程(cheng)(cheng)于(yu)2007年9月(yue)10日開工(gong)(gong)(gong)以(yi)來,葛(ge)洲(zhou)壩(ba)人科學組織,精心施工(gong)(gong)(gong),僅(jin)(jin)用15個月(yue)零7天(tian)(tian)就(jiu)使首臺機(ji)組順利(li)投產(chan)發(fa)(fa)電。而兩臺機(ji)組全(quan)部投產(chan)發(fa)(fa)電時間僅(jin)(jin)用了17個月(yue)17天(tian)(tian),再次(ci)創造了火電行業機(ji)組建(jian)設投產(chan)新(xin)紀錄(lu)。