文章來(lai)源:中國冶金科工集團公司 發布時間:2009-12-30
日前(qian),由中冶集團二(er)十冶施工(gong)(gong)的文安新鋼2*60T轉爐工(gong)(gong)程2號轉爐前(qian)鋼水花飛濺,爐口(kou)流出了(le)第一口(kou)鋼水,這標志著該工(gong)(gong)程成功地接(jie)受了(le)過(guo)鋼的考驗。新鋼工(gong)(gong)程是中冶二(er)十冶負責施工(gong)(gong)的綜合托管項目,自開(kai)工(gong)(gong)以來,經該項目部全體人員共同(tong)努力,科學組織,合理(li)安排施工(gong)(gong)工(gong)(gong)期,共完成土方142000余(yu)立,砼2400余(yu)立,結構制安9000余(yu)噸,設備安裝(zhuang)1000余(yu)噸,管道安裝(zhuang)10000余(yu)米(mi),各(ge)類(lei)閥門(men)安裝(zhuang)300臺(tai),電(dian)纜敷(fu)設38000余(yu)米(mi),各(ge)類(lei)儀表(biao)100余(yu)臺(tai)。