文章來源:中(zhong)國(guo)鐵(tie)路(lu)通信信號集團公司 發布(bu)時間:2009-11-26
中國通號集團堅持“總體布局、分段突擊、均衡生產、確保重點、快速推進”的原則,結合武廣客運專線工程實際優化組織、規范管理,科學施工,緊張有序地推進工作,目前,在參建員工的共同努力下,武廣客專綜合試驗段通信信號工程進度按照業主計劃實施,完成基本功能的聯調聯試。
正線(xian)全長968.57公里有18個車站的(de)武廣客(ke)運專線(xian)工(gong)(gong)程,預計于2009年8月31日全線(xian)竣工(gong)(gong)。面對緊張的(de)工(gong)(gong)程形勢,中國通號(hao)集團根(gen)據工(gong)(gong)程和綜(zong)合試(shi)(shi)驗段的(de)現狀,與(yu)設(she)(she)計、建設(she)(she)單位、地方政府(fu)聯系溝(gou)通,營造(zao)外部和諧施(shi)工(gong)(gong)環境;與(yu)站前單位聯系溝(gou)通,見縫插針交叉施(shi)工(gong)(gong);依據現有圖紙(zhi),進(jin)行估料,及時做(zuo)好(hao)物資(zi)設(she)(she)備(bei)儲備(bei)與(yu)供應;科(ke)學安排(pai)施(shi)工(gong)(gong)資(zi)源合理控制(zhi)各道(dao)工(gong)(gong)序,實(shi)現均衡(heng)生產,克服站前施(shi)工(gong)(gong)的(de)不利影(ying)響,尤其是他們(men)根(gen)據武廣客(ke)運專線(xian)綜(zong)合試(shi)(shi)驗段建設(she)(she)情況(kuang)建立的(de)信(xin)號(hao)工(gong)(gong)程仿(fang)真線(xian)路試(shi)(shi)驗基地,為員工(gong)(gong)掌握(wo)相關施(shi)工(gong)(gong)工(gong)(gong)藝、安裝方法、設(she)(she)備(bei)性能、安全防范要求,在(zai)工(gong)(gong)程進(jin)入(ru)實(shi)施(shi)階段快(kuai)速準確按(an)節點(dian)目標完(wan)成(cheng)施(shi)工(gong)(gong)提供了保障。