文章來源:中國冶金科工集團公司 發布時(shi)間:2009-10-27
10月22日,中冶長天衡鋼煉鐵系統燒結工程120米主煙囪提前竣工。在此之前,燒結主廠房混凝土結構已于10月19日完工。
中冶(ye)長天衡鋼(gang)煉鐵系統燒(shao)結工(gong)(gong)(gong)程120米主(zhu)煙(yan)囪(cong)(cong)、60米整(zheng)粒除(chu)(chu)塵(chen)煙(yan)囪(cong)(cong)和60米機(ji)尾(wei)除(chu)(chu)塵(chen)煙(yan)囪(cong)(cong)由北方三冶(ye)煙(yan)塔(ta)公司負責施工(gong)(gong)(gong)。其中,主(zhu)煙(yan)囪(cong)(cong)和整(zheng)粒除(chu)(chu)塵(chen)煙(yan)囪(cong)(cong)于7月(yue)6日(ri)開工(gong)(gong)(gong),機(ji)尾(wei)除(chu)(chu)塵(chen)煙(yan)囪(cong)(cong)于10月(yue)9日(ri)開工(gong)(gong)(gong)。整(zheng)粒除(chu)(chu)塵(chen)煙(yan)囪(cong)(cong)已于9月(yue)24日(ri)完(wan)工(gong)(gong)(gong),現主(zhu)煙(yan)囪(cong)(cong)提前(qian)(qian)竣工(gong)(gong)(gong)。目前(qian)(qian),該(gai)項(xiang)目整(zheng)粒電除(chu)(chu)塵(chen)、機(ji)尾(wei)電除(chu)(chu)塵(chen)、主(zhu)電除(chu)(chu)塵(chen)、燃料粗破碎、篩分(fen)取樣(yang)室和燒(shao)結主(zhu)廠房等(deng)混凝土結構已相繼完(wan)工(gong)(gong)(gong),土建工(gong)(gong)(gong)程也進入尾(wei)聲,設備和電氣安裝已陸續開始。項(xiang)目預計在2009年2月(yue)底投入運行。