文(wen)章來源:國家電網公司 發布時間:2009-07-31
7月(yue)25日(ri)20時(shi)57分,隨著倒送電試驗(yan)沖(chong)擊(ji)成(cheng)功,國內首條500千伏(fu)同(tong)塔雙(shuang)回(hui)海上(shang)大跨越(yue)輸(shu)電線(xian)路(lu)工程——福建莆田燃(ran)氣電廠—莆田變電站500千伏(fu)Ⅰ、Ⅱ回(hui)線(xian)路(lu)竣工,其中Ⅱ回(hui)線(xian)路(lu)投運(yun)。據了(le)解,7月(yue)28日(ri)22時(shi)登陸(lu)福清東(dong)瀚鎮的臺風“鳳凰(huang)”給莆田帶(dai)來了(le)狂(kuang)風暴雨(yu),但該工程運(yun)行穩定,未受臺風影響(xiang)。
該線路工(gong)(gong)(gong)程(cheng)(cheng)是國家重點工(gong)(gong)(gong)程(cheng)(cheng)莆田燃氣電(dian)廠的配套送(song)出(chu)工(gong)(gong)(gong)程(cheng)(cheng),也(ye)是福(fu)建電(dian)網接入新能源發電(dian)的里程(cheng)(cheng)碑工(gong)(gong)(gong)程(cheng)(cheng)。工(gong)(gong)(gong)程(cheng)(cheng)于2007年10月18日開(kai)工(gong)(gong)(gong),總投資3億多元,全(quan)長35.62千米,建塔82基(ji),其中17號~21號段跨越莆田湄洲灣海域,跨越長度為3.114千米。該工(gong)(gong)(gong)程(cheng)(cheng)由福(fu)建省(sheng)電(dian)力(li)設(she)計院自行設(she)計,福(fu)建省(sheng)第二電(dian)力(li)建設(she)公司(si)施工(gong)(gong)(gong)。工(gong)(gong)(gong)程(cheng)(cheng)投運后可有效提高福(fu)建電(dian)網安全(quan)穩定運行水平,緩解迎(ying)峰度夏壓力(li)。
據介紹,整個工程施工難度最大的(de)是(shi)跨(kua)海(hai)(hai)段,具有鐵塔(ta)高、跨(kua)度寬、基(ji)礎(chu)大等特點(dian),其中(zhong)位(wei)于湄洲灣(wan)海(hai)(hai)域的(de)直(zhi)線大跨(kua)越(yue)塔(ta)19號塔(ta)是(shi)我國第一基(ji)500千伏海(hai)(hai)上鐵塔(ta),塔(ta)高128.5米,重(zhong)651.55噸。海(hai)(hai)中(zhong)鐵塔(ta)基(ji)礎(chu)不僅要承受(shou)垂直(zhi)荷載,還要承受(shou)多(duo)(duo)(duo)方向較(jiao)大水平(ping)荷載,樁(zhuang)(zhuang)基(ji)露出海(hai)(hai)平(ping)面較(jiao)多(duo)(duo)(duo),必須具有較(jiao)大的(de)水平(ping)剛度。設(she)計人(ren)員(yuan)反復比較(jiao)分(fen)析,最終(zhong)采用(yong)了鋼(gang)管樁(zhuang)(zhuang)基(ji)礎(chu),這也是(shi)國內首(shou)次在500千伏線路建設(she)上采用(yong)此(ci)方案。此(ci)外,設(she)計人(ren)員(yuan)還取得了鋼(gang)管樁(zhuang)(zhuang)防(fang)(fang)腐、鐵塔(ta)基(ji)礎(chu)防(fang)(fang)風(feng)防(fang)(fang)浪(lang)、鐵塔(ta)基(ji)礎(chu)防(fang)(fang)撞等多(duo)(duo)(duo)個課題的(de)研究成果。
跨海(hai)段施(shi)工是(shi)對電力(li)基建(jian)施(shi)工實力(li)的(de)(de)大考驗。在(zai)海(hai)面(mian)百米高空之上(shang)作業(ye),正常情(qing)況下(xia)風力(li)達6~7級(ji),天氣略(lve)有變化風力(li)就(jiu)會超過(guo)7級(ji);海(hai)上(shang)作業(ye)面(mian)窄,鋼(gang)管構件又(you)(you)長又(you)(you)重,運輸困(kun)難(nan)(nan),組立技術要求高,安(an)全控制更難(nan)(nan);再加上(shang)至少需(xu)要15個月(yue)的(de)(de)工期(qi)被壓縮成9個月(yue),施(shi)工難(nan)(nan)度可想而知。
針對工程特點,福建公(gong)司大膽采(cai)用(yong)新工藝、新技術(shu)、新裝(zhuang)備,提高(gao)施(shi)工質量和(he)效率。例如,海上鐵塔組立(li)施(shi)工方案采(cai)用(yong)數(shu)字化(hua)立(li)體動(dong)態模擬;地面工作人員使用(yong)高(gao)塔施(shi)工視頻監控系統(tong),實時查看(kan)施(shi)工現場變化(hua)和(he)人員行為,消除隱患。
施(shi)(shi)工(gong)(gong)單位強化了(le)高塔(ta)施(shi)(shi)工(gong)(gong)安(an)(an)全(quan)(quan)技(ji)術措施(shi)(shi),在(zai)(zai)塔(ta)身內外設置(zhi)(zhi)安(an)(an)全(quan)(quan)網,在(zai)(zai)垂直方向(xiang)設置(zhi)(zhi)攀爬(pa)自鎖裝置(zhi)(zhi),在(zai)(zai)水(shui)平(ping)方向(xiang)上設置(zhi)(zhi)水(shui)平(ping)扶手,使(shi)用(yong)全(quan)(quan)方位的防沖擊(ji)安(an)(an)全(quan)(quan)帶及速(su)差保護器,使(shi)高空作(zuo)業人員(yuan)處(chu)于(yu)全(quan)(quan)面(mian)保護中。針(zhen)對福(fu)建(jian)多臺(tai)風的氣候條件,施(shi)(shi)工(gong)(gong)單位組織(zhi)了(le)海上安(an)(an)全(quan)(quan)應急預(yu)案演(yan)練,提高施(shi)(shi)工(gong)(gong)人員(yuan)自防自救能(neng)力。福(fu)建(jian)公司還(huan)對參(can)加跨(kua)海段(duan)施(shi)(shi)工(gong)(gong)的技(ji)術骨干進行了(le)封閉式(shi)軍訓(xun),以提高協作(zuo)能(neng)力和現(xian)場管理(li)水(shui)平(ping)。
在9個月艱(jian)苦施工(gong)后,福建(jian)電力鐵軍最(zui)終實現了“工(gong)期零(ling)(ling)拖延、安(an)全(quan)零(ling)(ling)事(shi)故、質(zhi)量零(ling)(ling)缺陷”的目標(biao)。