文(wen)章來源:國(guo)家電網公司 發布時間(jian):2009-06-25
6月16日,500千伏(fu)浙江王店(dian)——嘉善線(xian)路增容改造工程啟動投運。至(zhi)此(ci),宣告(gao)華(hua)東(dong)電網迎峰度(du)夏500千伏(fu)輸變(bian)電工程建設(she)任務基本完(wan)成。
為華東電網迎峰(feng)度夏(xia)所需,多項供電工(gong)(gong)程目前已經成(cheng)(cheng)(cheng)功(gong)建(jian)(jian)成(cheng)(cheng)(cheng)投運。其中包括安(an)徽西(xi)通道輸變電工(gong)(gong)程、安(an)徽馬鞍山—江蘇錫(xi)西(xi)南線路工(gong)(gong)程、上(shang)海500千伏串聯(lian)電抗器工(gong)(gong)程、浙江嘉王(wang)線增(zeng)容改造工(gong)(gong)程等重點項目。華東全網共建(jian)(jian)成(cheng)(cheng)(cheng)投運500千伏變電容量1200萬千伏安(an),完成(cheng)(cheng)(cheng)率(lv)95%;線路1694公里,完成(cheng)(cheng)(cheng)率(lv)80%。全網工(gong)(gong)程預計于(yu)6月內可全面建(jian)(jian)成(cheng)(cheng)(cheng)投運,這將進一(yi)步提(ti)高華東電網迎峰(feng)度夏(xia)安(an)全穩(wen)定供電能力。
2008年(nian)華東電(dian)網輸變電(dian)工(gong)(gong)程建設(she)工(gong)(gong)作異(yi)常艱難,一是受年(nian)初冰雪(xue)災害影(ying)響(xiang),設(she)備(bei)材料供應緊(jin)張;二(er)是停電(dian)施工(gong)(gong)安排(pai)困難,對施工(gong)(gong)方案的調整(zheng)影(ying)響(xiang)了工(gong)(gong)程進(jin)度(du);三是線(xian)路(lu)交叉跨(kua)越多,對一些線(xian)路(lu)須進(jin)行升高改造(zao);四是社會(hui)協調工(gong)(gong)作多,路(lu)徑(jing)改道經(jing)常發生(sheng);五是工(gong)(gong)期緊(jin)張,一些工(gong)(gong)程實際核(he)準(zhun)工(gong)(gong)期,大大少于常規工(gong)(gong)期。
在異常艱難(nan)的情況下,華(hua)東(dong)電(dian)網全(quan)體建(jian)(jian)設者(zhe)們發揚(yang)頑強拼(pin)搏、團結建(jian)(jian)網的精神,終于(yu)安全(quan)、優質、如期地完成(cheng)了各項迎峰(feng)度夏輸變電(dian)工程建(jian)(jian)設,為建(jian)(jian)設堅強電(dian)網創造了新(xin)成(cheng)績,為華(hua)東(dong)電(dian)網安全(quan)穩(wen)定(ding)供(gong)電(dian)作出了新(xin)貢獻。