文章來源(yuan):中國南(nan)方電網有限責任公司 發布時間(jian):2009-06-24
日前,云南電網昆明供電局圓滿完成10千伏沙鍋村線改造工程,使西山區海口、碧雞等地供電能力提高一倍多,近2萬戶居民、94個工礦企業受益。
5月初,昆明供(gong)電(dian)(dian)局(ju)安(an)排600萬元資金實施改(gai)造工(gong)(gong)程(cheng),用兩天(tian)(tian)時間全部拆除原(yuan)線路,新建一條7公里雙(shuang)回路供(gong)電(dian)(dian)線路。為盡(jin)量減少停電(dian)(dian)對客戶影響(xiang),昆明供(gong)電(dian)(dian)局(ju)反(fan)復研究工(gong)(gong)程(cheng)方(fang)案,將原(yuan)需20多天(tian)(tian)“早停晚送”方(fang)案改(gai)為2-3天(tian)(tian)“全停快(kuai)送”,經過周密(mi)策劃、高(gao)效指揮,組(zu)織多家施工(gong)(gong)單位800多人同時進場施工(gong)(gong),確保(bao)了工(gong)(gong)程(cheng)安(an)全、優質圓滿完成。