文章來源:中國(guo)核工業集團公司 發(fa)布(bu)時間:2009-05-29
5月22日,國(guo)家核安(an)全局(ju)組織的專(zhuan)家組對福清核電項目1、2號(hao)(hao)機組核島基坑負(fu)挖工程(cheng)(cheng)進行(xing)(xing)了(le)核安(an)全檢查(cha)。通過(guo)檢查(cha),專(zhuan)家組認為,工程(cheng)(cheng)施工過(guo)程(cheng)(cheng)質量得到了(le)有(you)效(xiao)控制。1、2號(hao)(hao)機組具備了(le)按照工程(cheng)(cheng)計(ji)劃進行(xing)(xing)核島土(tu)建(jian)施工的條件。
福清核電項目1、2號機(ji)組核島負挖工(gong)(gong)(gong)(gong)程于2007年(nian)12月(yue)11日正式開工(gong)(gong)(gong)(gong),于2008年(nian)5月(yue)9日完工(gong)(gong)(gong)(gong),負挖工(gong)(gong)(gong)(gong)程量為14萬余(yu)立(li)方(fang)米。在(zai)施工(gong)(gong)(gong)(gong)過(guo)程中,項目總(zong)承包方(fang)——中國核電工(gong)(gong)(gong)(gong)程有限公司按(an)照工(gong)(gong)(gong)(gong)程總(zong)體進度計劃(hua),嚴格執(zhi)行(xing)項目四大控制(zhi),順(shun)利完成了負挖工(gong)(gong)(gong)(gong)程。