文章來源:國家電網公司 發(fa)布(bu)時間:2009-03-07
3月6日18時,經過6500多名搶險隊員(yuan)一個多月的(de)奮力(li)搶修,三(san)峽電(dian)(dian)(dian)力(li)南送(song)廣(guang)(guang)東的(de)輸電(dian)(dian)(dian)大動脈±500千伏江(jiang)城直流輸電(dian)(dian)(dian)線(xian)路提前恢復運行。江(jiang)城線(xian)恢復送(song)電(dian)(dian)(dian),可(ke)填補(bu)廣(guang)(guang)東省近三(san)分之一的(de)電(dian)(dian)(dian)力(li)缺口,廣(guang)(guang)東電(dian)(dian)(dian)網電(dian)(dian)(dian)力(li)緊缺形(xing)勢(shi)得(de)到極大緩解。
江城線北起(qi)湖北荊州(zhou)江陵換流(liu)站(zhan),南至廣(guang)東(dong)惠(hui)州(zhou)鵝城換流(liu)站(zhan),輸電容量300萬千瓦。1月中旬(xun),冰(bing)雪災害造成江城線多處損(sun)毀。
為早日修復江城線(xian)(xian), 國(guo)家電(dian)網公司緊急抽調山東、河北、江蘇、安徽、青(qing)海等省(sheng)電(dian)力公司共(gong)6500多名搶(qiang)修人員趕(gan)赴(fu)搶(qiang)修現(xian)場。至通(tong)電(dian)當日,共(gong)重新組立鐵(tie)塔43基,消除一般(ban)缺陷(xian)等就363處,架設導線(xian)(xian)32.4千米、地線(xian)(xian)123.8千米、光纜151.2千米,提前4天完成了(le)搶(qiang)修任(ren)務。