文章來源:中國兵器工業集團公(gong)司(si) 發(fa)布時(shi)間:2010-06-11
經過萬余名建設(she)者(zhe)22個(ge)月(yue)的艱苦奮戰,中國兵器工(gong)業集(ji)團華錦公(gong)司“十一五”重(zhong)點工(gong)程(cheng)建設(she)全(quan)面(mian)完成了(le)打樁(zhuang)、基礎和(he)地管、結(jie)構和(he)設(she)備(bei)安(an)(an)裝、工(gong)藝管線和(he)電(dian)纜敷設(she)和(he)電(dian)氣(qi)設(she)備(bei)安(an)(an)裝5個(ge)階段的全(quan)部(bu)施工(gong)任務,截止到5月(yue)31日,多(duo)個(ge)項目陸續(xu)驗收,勝(sheng)利實(shi)現機械竣工(gong)。
儲運工程實現全線機械竣工
5月31日,該公司“十(shi)一(yi)五”重點工(gong)(gong)(gong)程(cheng)(cheng)(cheng)之(zhi)一(yi)的儲運(yun)155公里輸(shu)油(you)管線順利通(tong)過竣(jun)(jun)(jun)工(gong)(gong)(gong)驗(yan)收,至此(ci),“十(shi)一(yi)五” 工(gong)(gong)(gong)程(cheng)(cheng)(cheng)的關鍵項(xiang)目(mu)——儲運(yun)工(gong)(gong)(gong)程(cheng)(cheng)(cheng)實(shi)現全線機(ji)械竣(jun)(jun)(jun)工(gong)(gong)(gong),這(zhe)也是(shi)“十(shi)一(yi)五”工(gong)(gong)(gong)程(cheng)(cheng)(cheng)第一(yi)個整體竣(jun)(jun)(jun)工(gong)(gong)(gong)的項(xiang)目(mu)。自2008年3月1日儲運(yun)工(gong)(gong)(gong)程(cheng)(cheng)(cheng)開工(gong)(gong)(gong)建設以來,按照(zhao)“打造兵器石化產業(ye)精(jing)品工(gong)(gong)(gong)程(cheng)(cheng)(cheng)”要求(qiu),堅持嚴(yan)之(zhi)又(you)嚴(yan)、細之(zhi)又(you)細、實(shi)之(zhi)又(you)實(shi)的管理思路,多方協調化解矛(mao)盾,嚴(yan)密(mi)推進施工(gong)(gong)(gong)進度,嚴(yan)肅過程(cheng)(cheng)(cheng)質(zhi)量控制,嚴(yan)格保證(zheng)施工(gong)(gong)(gong)安全。克服(fu)時(shi)間緊、任(ren)務(wu)重、建設環(huan)境復(fu)雜(za)、管線穿越路河難(nan)度大等實(shi)際困難(nan),高標(biao)準、高質(zhi)量完成了工(gong)(gong)(gong)程(cheng)(cheng)(cheng)建設任(ren)務(wu),實(shi)現全線機(ji)械竣(jun)(jun)(jun)工(gong)(gong)(gong)。
乙烯工程雙聚裝置順利通過驗收
5月(yue)30日(ri),該(gai)公司“十一五”重點工程(cheng)(cheng)之一的(de)(de)(de)乙烯工程(cheng)(cheng)聚(ju)乙烯、聚(ju)丙烯兩大主(zhu)體裝置(zhi)雙雙通過(guo)總指揮部驗收,這是乙烯工程(cheng)(cheng)率先通過(guo)驗收的(de)(de)(de)主(zhu)體裝置(zhi)。“雙聚(ju)”項目于2008年2月(yue)14日(ri)正式(shi)開工建(jian)設,在(zai)15個(ge)月(yue)的(de)(de)(de)施(shi)(shi)工建(jian)設中,全體建(jian)設人員克服工期短、設備到貨晚、雨季施(shi)(shi)工、設計變(bian)更等多重困難,精(jing)心(xin)組織,晝夜施(shi)(shi)工,強力推進施(shi)(shi)工進度(du)。在(zai)搶抓施(shi)(shi)工進度(du)的(de)(de)(de)同時,嚴(yan)控施(shi)(shi)工質(zhi)量(liang),狠抓安全施(shi)(shi)工,特別是進入(ru)驗收階段,按照(zhao)“三查(cha)四定”要求,嚴(yan)查(cha)問題,深刻整改,確保了工程(cheng)(cheng)的(de)(de)(de)順利竣工驗收。
乙烯總變電所勝利報捷
5月27日(ri),已投用三(san)個多月的該公(gong)司乙(yi)烯總變電(dian)(dian)所順利通過機械竣工(gong)驗(yan)(yan)收。按照工(gong)程建設“電(dian)(dian)氣先(xian)行(xing)”的部(bu)署和要(yao)求,他們先(xian)后戰勝了設計滯后造成工(gong)程被迫停工(gong)、大風雪影響電(dian)(dian)纜敷設等困難,搶工(gong)期,抓質量,在2009年1月12日(ri)具備受電(dian)(dian)條件的基礎上,于2月25日(ri)實現7臺變壓器全(quan)部(bu)具備向乙(yi)烯各(ge)分(fen)變電(dian)(dian)所送電(dian)(dian)條件。隨(sui)著100余項問題的徹底(di)整改(gai),乙(yi)烯總變電(dian)(dian)所全(quan)面(mian)通過竣工(gong)驗(yan)(yan)收。
油化成品油罐區實現機械竣工
5月29日,該公司油化成(cheng)品(pin)油罐(guan)區(qu)順利(li)通過(guo)竣工(gong)驗(yan)收(shou),實現機(ji)械(xie)竣工(gong)。自(zi)2008年3月28日油化成(cheng)品(pin)油罐(guan)區(qu)破土動工(gong)以來,公司克服(fu)時(shi)間緊(jin)、任務(wu)重、設(she)計(ji)變(bian)更(geng)以及(ji)材料到貨(huo)滯后等諸多不利(li)因素,科學(xue)組織,頑強拼(pin)搏,在確(que)保安(an)全和(he)質量(liang)的(de)前提下,力(li)搶工(gong)期,先后完成(cheng)了(le)“5.30”基礎施工(gong)和(he)“9.30”罐(guan)體制作以及(ji)設(she)備及(ji)工(gong)藝管線安(an)裝、水壓試(shi)驗(yan)、單機(ji)試(shi)車(che)等各階段節點目標。目前,油化成(cheng)品(pin)油罐(guan)區(qu)已(yi)具備試(shi)生產條件。
乙烯水系統全線竣工并投入運行
由該公司乙烯(xi)(xi)(xi)給水(shui)(shui)(shui)及高(gao)壓消防水(shui)(shui)(shui)泵站(zhan)、乙烯(xi)(xi)(xi)雨(yu)水(shui)(shui)(shui)池、污水(shui)(shui)(shui)泵站(zhan)、第二熱水(shui)(shui)(shui)站(zhan)、脫(tuo)鹽水(shui)(shui)(shui)站(zhan)、給水(shui)(shui)(shui)變電所和乙烯(xi)(xi)(xi)第一、二循環水(shui)(shui)(shui)場等(deng)8個單體項(xiang)目組(zu)成的乙烯(xi)(xi)(xi)水(shui)(shui)(shui)系統實現全線(xian)告捷(jie),順利通過竣工(gong)(gong)驗收(shou)(shou)并(bing)已投(tou)入生(sheng)產(chan)運行。其中,前6個單體項(xiang)目被評為“十(shi)一五”精品工(gong)(gong)程。施工(gong)(gong)中,他們(men)克服建筑結構復雜、作業面(mian)分散、材料到貨(huo)滯后、交叉作業多等(deng)諸多困難,高(gao)標準、高(gao)質(zhi)量推進工(gong)(gong)程進度。特別(bie)是在收(shou)(shou)尾驗收(shou)(shou)中,他們(men)嚴格自檢自查,查出并(bing)徹底整(zheng)改問題2700余項(xiang),確保了(le)水(shui)(shui)(shui)汽(qi)項(xiang)目的高(gao)標準、高(gao)質(zhi)量竣工(gong)(gong)。
公用供熱外管廊實現機械竣工
5月31日,該公司公用供熱(re)外管廊(lang)順利通過驗收復查,實現機械竣工。該項目于(yu)2008年3月11日開工,經過廣(guang)大建設者14個月的(de)艱苦奮戰,完(wan)成管樁(zhuang)施(shi)工632根,澆筑混凝土1100立(li)方(fang)米(mi),制作安裝(zhuang)鋼結構(gou)1700噸,鋪(pu)設各類管線27條約15000延長米(mi),完(wan)成保(bao)溫絕(jue)熱(re)工程(cheng)3200立(li)方(fang)米(mi)。特別(bie)是攻克(ke)了(le)冬季施(shi)工難(nan)題,保(bao)質保(bao)量保(bao)進(jin)度完(wan)成了(le)1020米(mi)φ711高壓(ya)管線施(shi)工,確保(bao)了(le)供熱(re)外管廊(lang)工程(cheng)的(de)高標(biao)準(zhun)、高質量、高效率竣工。