文章(zhang)來(lai)源(yuan):國家電網(wang)公司 發布(bu)時間:2009-07-31
7月29日上(shang)(shang)午,重慶(qing)市(shi)電力公司援建(jian)四川(chuan)松潘(pan)縣(xian)電網災后(hou)恢復重建(jian)工(gong)程竣工(gong)。在竣工(gong)和歡送(song)儀式上(shang)(shang),松潘(pan)縣(xian)縣(xian)委書(shu)記黃芝林(lin)向援建(jian)隊伍送(song)上(shang)(shang)飽含(han)松潘(pan)人民感謝之(zhi)情(qing)的錦旗,藏族(zu)群(qun)眾為電網員工(gong)獻上(shang)(shang)潔白(bai)的哈達(da)。
汶(wen)川(chuan)大地震使(shi)松(song)潘(pan)縣電(dian)網遭(zao)受嚴重(zhong)(zhong)損失。重(zhong)(zhong)慶公(gong)司(si)高(gao)度重(zhong)(zhong)視(shi)松(song)潘(pan)電(dian)網搶(qiang)修和(he)恢復重(zhong)(zhong)建(jian)工(gong)程,按照國家(jia)電(dian)網公(gong)司(si)統一部署,從所屬永川(chuan)供電(dian)局(ju)先后派出兩批78名援建(jian)人員和(he)14臺施工(gong)車輛,奔(ben)赴松(song)潘(pan)毛(mao)爾蓋革命老(lao)區。從6月12日起,援建(jian)隊員克服海拔高(gao)、道路崎嶇、氣候惡劣等困(kun)難,夜以繼日抓緊施工(gong),奮(fen)戰40多天(tian),提(ti)前10天(tian)高(gao)質(zhi)量(liang)地完成了援建(jian)任務,讓毛(mao)爾蓋3個(ge)鄉(xiang)900余戶5000多名居(ju)民用上了安全可靠的電(dian)能。
在(zai)竣工(gong)歡送儀式前(qian)一天,毛爾蓋(gai)地(di)區上八寨鄉的藏族(zu)同(tong)胞自發(fa)組織起來,為即將離開的電網員工(gong)送行。