文章來源:國家電網公司(si)  發布時間(jian):2009-07-31

  7月25日20時57分,隨著倒送電試驗沖(chong)擊(ji)成(cheng)功,國內(nei)首條500千(qian)(qian)伏同塔雙(shuang)回(hui)海上(shang)大(da)跨越輸電線路工(gong)程(cheng)——福建莆田燃氣(qi)電廠(chang)—莆田變電站500千(qian)(qian)伏Ⅰ、Ⅱ回(hui)線路竣工(gong),其中Ⅱ回(hui)線路投運。據了解,7月28日22時登(deng)陸(lu)福清東(dong)瀚(han)鎮的臺風(feng)(feng)“鳳凰”給莆田帶來了狂(kuang)風(feng)(feng)暴雨,但該工(gong)程(cheng)運行穩(wen)定,未受臺風(feng)(feng)影響。

  該線路工(gong)(gong)程(cheng)是國(guo)家重(zhong)點工(gong)(gong)程(cheng)莆田(tian)燃(ran)氣電廠的配套送(song)出工(gong)(gong)程(cheng),也是福(fu)建(jian)(jian)(jian)電網接(jie)入新能源發電的里程(cheng)碑工(gong)(gong)程(cheng)。工(gong)(gong)程(cheng)于(yu)2007年(nian)10月18日開工(gong)(gong),總投資(zi)3億多元,全長35.62千米(mi),建(jian)(jian)(jian)塔82基,其中17號~21號段跨越莆田(tian)湄洲(zhou)灣(wan)海(hai)域,跨越長度為(wei)3.114千米(mi)。該工(gong)(gong)程(cheng)由(you)福(fu)建(jian)(jian)(jian)省(sheng)電力設計院自(zi)行(xing)設計,福(fu)建(jian)(jian)(jian)省(sheng)第二電力建(jian)(jian)(jian)設公(gong)司施工(gong)(gong)。工(gong)(gong)程(cheng)投運后可(ke)有效提高福(fu)建(jian)(jian)(jian)電網安(an)全穩定(ding)運行(xing)水平,緩解(jie)迎(ying)峰度夏壓力。

  據介紹,整(zheng)個(ge)工(gong)程施工(gong)難(nan)度(du)最(zui)大(da)(da)的是(shi)(shi)跨(kua)海(hai)(hai)段,具(ju)有(you)鐵(tie)塔(ta)(ta)(ta)高、跨(kua)度(du)寬、基(ji)礎(chu)大(da)(da)等特點,其中位(wei)于湄洲(zhou)灣海(hai)(hai)域(yu)的直線大(da)(da)跨(kua)越塔(ta)(ta)(ta)19號(hao)塔(ta)(ta)(ta)是(shi)(shi)我國(guo)第一(yi)基(ji)500千伏海(hai)(hai)上鐵(tie)塔(ta)(ta)(ta),塔(ta)(ta)(ta)高128.5米,重(zhong)651.55噸。海(hai)(hai)中鐵(tie)塔(ta)(ta)(ta)基(ji)礎(chu)不僅要(yao)承(cheng)(cheng)受(shou)(shou)垂直荷載,還要(yao)承(cheng)(cheng)受(shou)(shou)多(duo)方向較大(da)(da)水(shui)平(ping)荷載,樁基(ji)露出海(hai)(hai)平(ping)面較多(duo),必須具(ju)有(you)較大(da)(da)的水(shui)平(ping)剛度(du)。設計(ji)人(ren)員反復比(bi)較分析,最(zui)終采用了鋼(gang)管樁基(ji)礎(chu),這也是(shi)(shi)國(guo)內首次在(zai)500千伏線路建設上采用此(ci)方案。此(ci)外,設計(ji)人(ren)員還取得了鋼(gang)管樁防(fang)腐、鐵(tie)塔(ta)(ta)(ta)基(ji)礎(chu)防(fang)風防(fang)浪、鐵(tie)塔(ta)(ta)(ta)基(ji)礎(chu)防(fang)撞等多(duo)個(ge)課題的研(yan)究(jiu)成果。

  跨(kua)海段施(shi)工(gong)(gong)是(shi)對(dui)電力基(ji)建(jian)施(shi)工(gong)(gong)實力的大考驗(yan)。在(zai)海面(mian)百米高(gao)空之(zhi)上作業,正(zheng)常情況下風力達6~7級,天氣略有變化風力就(jiu)會超過(guo)7級;海上作業面(mian)窄,鋼管構件又長(chang)又重,運輸困難,組立技(ji)術要求高(gao),安全(quan)控制(zhi)更難;再加上至少需要15個(ge)月的工(gong)(gong)期被(bei)壓(ya)縮成9個(ge)月,施(shi)工(gong)(gong)難度可想而知。

  針(zhen)對工(gong)(gong)程特(te)點,福建公司大膽(dan)采用新(xin)工(gong)(gong)藝、新(xin)技術、新(xin)裝備,提高(gao)施工(gong)(gong)質量和效率。例(li)如,海上鐵塔(ta)組立施工(gong)(gong)方案(an)采用數(shu)字化立體動態模擬;地面工(gong)(gong)作人員(yuan)使用高(gao)塔(ta)施工(gong)(gong)視頻監控系統,實時(shi)查看施工(gong)(gong)現(xian)場變(bian)化和人員(yuan)行為,消除隱(yin)患。

  施工(gong)(gong)(gong)單位(wei)強化(hua)了高塔(ta)施工(gong)(gong)(gong)安全技(ji)術措施,在(zai)塔(ta)身內(nei)外設置(zhi)(zhi)安全網,在(zai)垂直方向(xiang)設置(zhi)(zhi)攀爬自鎖裝置(zhi)(zhi),在(zai)水平方向(xiang)上設置(zhi)(zhi)水平扶手,使用全方位(wei)的防沖(chong)擊安全帶(dai)及速差保(bao)護器(qi),使高空作業人員(yuan)處于全面保(bao)護中。針(zhen)對(dui)福建多臺風的氣(qi)候條件,施工(gong)(gong)(gong)單位(wei)組織了海(hai)上安全應急(ji)預(yu)案演練,提高施工(gong)(gong)(gong)人員(yuan)自防自救能(neng)力(li)。福建公司還對(dui)參加(jia)跨(kua)海(hai)段施工(gong)(gong)(gong)的技(ji)術骨干進(jin)行(xing)了封閉(bi)式軍訓,以提高協(xie)作能(neng)力(li)和現(xian)場管理水平。

  在(zai)9個月艱苦施工(gong)后(hou),福(fu)建(jian)電(dian)力鐵軍(jun)最終實現了(le)“工(gong)期零拖(tuo)延、安全零事故、質量零缺陷”的目標。