文章來源:中國水利水電建設(she)集團公(gong)司 發布時間:2009-07-30
中國水電集團承建的貴州構皮灘工程克服年初冰災影響工期兩個多月的不利局面,日前如期完成防洪度汛目標和節點工期,大壩混凝土澆筑38萬方,最大壩高已達EL632高程,向9月底下閘蓄水目標邁出了堅實一步。
構皮灘電(dian)(dian)(dian)站(zhan)(zhan)是貴州實(shi)施“西電(dian)(dian)(dian)東送”的(de)(de)標(biao)志性工(gong)(gong)(gong)(gong)程,是烏江干(gan)流上最(zui)(zui)(zui)大的(de)(de)梯級電(dian)(dian)(dian)站(zhan)(zhan)。水(shui)庫正常蓄水(shui)位630米,最(zui)(zui)(zui)大壩(ba)高232.5米,電(dian)(dian)(dian)站(zhan)(zhan)裝機300萬千瓦,多年平均(jun)發(fa)電(dian)(dian)(dian)量96.67億千瓦時(shi)(shi),以(yi)(yi)發(fa)電(dian)(dian)(dian)為主,兼顧航運(yun)、防洪及(ji)其他綜(zong)合(he)利用(yong),是烏江上最(zui)(zui)(zui)大的(de)(de)水(shui)電(dian)(dian)(dian)站(zhan)(zhan)。受年初(chu)雪(xue)凝災害影響,通往電(dian)(dian)(dian)站(zhan)(zhan)的(de)(de)供電(dian)(dian)(dian)線(xian)(xian)路出現(xian)(xian)(xian)多處鐵塔、電(dian)(dian)(dian)桿倒(dao)掉(diao),構皮灘電(dian)(dian)(dian)站(zhan)(zhan)被迫全(quan)部停(ting)工(gong)(gong)(gong)(gong)。工(gong)(gong)(gong)(gong)程延誤工(gong)(gong)(gong)(gong)期70余天,給施工(gong)(gong)(gong)(gong)生(sheng)(sheng)產(chan)(chan)帶來了(le)巨大的(de)(de)工(gong)(gong)(gong)(gong)期壓力。工(gong)(gong)(gong)(gong)程建(jian)設者們(men)仔(zi)細研究工(gong)(gong)(gong)(gong)期目(mu)標(biao),將任務細化分(fen)解,強(qiang)化生(sheng)(sheng)產(chan)(chan)現(xian)(xian)(xian)場(chang)管理,靈活(huo)調(diao)度(du)現(xian)(xian)(xian)場(chang)所有資源,抓住大壩(ba)澆筑(zhu)(zhu)這條主線(xian)(xian),順(shun)(shun)利完成了(le)防洪度(du)汛目(mu)標(biao)。另一方(fang)(fang)面,他們(men)根據今年施工(gong)(gong)(gong)(gong)生(sheng)(sheng)產(chan)(chan)特點,仔(zi)細研究生(sheng)(sheng)產(chan)(chan)現(xian)(xian)(xian)狀,及(ji)時(shi)(shi)調(diao)度(du)現(xian)(xian)(xian)場(chang)資源,隊(dui)與隊(dui)之間互相配合(he),相互支援(yuan),施工(gong)(gong)(gong)(gong)部牽頭(tou)堅持每天在施工(gong)(gong)(gong)(gong)現(xian)(xian)(xian)場(chang)召開(kai)碰頭(tou)會,及(ji)時(shi)(shi)調(diao)整生(sheng)(sheng)產(chan)(chan)作(zuo)業計劃(hua),解決現(xian)(xian)(xian)場(chang)出現(xian)(xian)(xian)的(de)(de)各種(zhong)問題,保持混凝土(tu)生(sheng)(sheng)產(chan)(chan)“一條龍”的(de)(de)順(shun)(shun)利進行(xing),進入夏季以(yi)(yi)來,職工(gong)(gong)(gong)(gong)們(men)頂著炎(yan)炎(yan)烈日,扎實(shi)苦干(gan),總結經(jing)驗,加速倉面準(zhun)備工(gong)(gong)(gong)(gong)作(zuo),一天同(tong)時(shi)(shi)開(kai)幾個倉面,加快開(kai)倉速度(du),不斷刷新開(kai)倉紀(ji)錄(lu)和臺班產(chan)(chan)量紀(ji)錄(lu),7月24日澆筑(zhu)(zhu)5個工(gong)(gong)(gong)(gong)作(zuo)面,臺班單產(chan)(chan)2500m3,日產(chan)(chan)4600 m3,創今年以(yi)(yi)來混凝土(tu)生(sheng)(sheng)產(chan)(chan)最(zui)(zui)(zui)好水(shui)平。連(lian)續幾個月來保持在澆筑(zhu)(zhu)7萬方(fang)(fang)混凝土(tu)的(de)(de)紀(ji)錄(lu),到目(mu)前為止,共(gong)完成壩(ba)體混凝土(tu)澆筑(zhu)(zhu)38萬方(fang)(fang)。