文(wen)章(zhang)來源(yuan):國家電(dian)網公司 發布時間:2009-06-20
6月16日(ri)8時,浙(zhe)江(jiang)電(dian)網500千伏嘉善—王店增容(rong)改造工程竣工投(tou)產,可進一步(bu)完(wan)善浙(zhe)北地區(qu)電(dian)網構架,緩解今夏華東地區(qu)用電(dian)緊張的壓力。
該(gai)工(gong)(gong)程(cheng)(cheng)為華東電網迎峰(feng)度夏重點工(gong)(gong)程(cheng)(cheng),按同桿(gan)雙回路(lu)設計,線路(lu)新建雙回路(lu)鐵(tie)塔91基,架設線路(lu)57.2千米。負責(ze)施(shi)工(gong)(gong)的浙江送變電工(gong)(gong)程(cheng)(cheng)公司送電一公司嘉興項目部(bu)施(shi)工(gong)(gong)隊(dui)員(yuan)克服(fu)時(shi)間緊(jin)、工(gong)(gong)程(cheng)(cheng)量(liang)大、跨越多等困難(nan),努力與(yu)當地政府(fu)群眾協調溝通(tong),優化人力、物資、設備管理,推(tui)進工(gong)(gong)程(cheng)(cheng)施(shi)工(gong)(gong)有序、高(gao)效開展。
面對繁重的施(shi)工任務(wu),該項(xiang)目(mu)部在確保安全的前(qian)提(ti)下倒(dao)排(pai)工期,成立工程突擊隊,實施(shi)夜間作業。施(shi)工隊員經過科學論證,采用“一個牽(qian)張段兩套設備同(tong)時開機”的方法,創(chuang)造了(le)“一天架設線路(lu)10千米(折合單根(gen)導線120千米)”的施(shi)工新紀錄。