文章來(lai)源:中國(guo)水利水電建設(she)集團公司 發布時間:2008-12-05
11月29日(ri),由中國水電建設集團水電一局承(cheng)建的小(xiao)灣水電站(zhan)泄(xie)洪(hong)洞土建及金屬結構安(an)裝(zhuang)工程(cheng)提前33天,勝利實現(xian)貫通(tong),標志著工程(cheng)進入了一個(ge)嶄新(xin)的施(shi)工階段。
小灣水電站泄洪(hong)洞(dong)(dong)全(quan)長1535.463米(mi),泄洪(hong)洞(dong)(dong)洞(dong)(dong)身為(wei)有(you)壓(ya)變無壓(ya)“龍抬頭(tou)”布置,由進水口、有(you)壓(ya)段、工(gong)作閘門(men)室、龍抬頭(tou)段、直槽斜坡(po)段及出口挑(tiao)流鼻坎組成(cheng)。
泄洪洞工(gong)(gong)(gong)(gong)程是小灣(wan)水(shui)電站最后一個(ge)土(tu)建主體工(gong)(gong)(gong)(gong)程,也是參建施工(gong)(gong)(gong)(gong)最大節點目標。為(wei)此,中國水(shui)電一局小灣(wan)項(xiang)目部(bu)以創(chuang)建精(jing)品為(wei)目標,精(jing)心組織(zhi)施工(gong)(gong)(gong)(gong)、優化(hua)資(zi)源配置、強化(hua)過(guo)程控制、嚴(yan)抓質量和安全;面(mian)對洞身長、斷面(mian)大、地質條件(jian)差(cha)、洞型(xing)復雜(za)多(duo)變、通風排煙難(nan)、施工(gong)(gong)(gong)(gong)干擾(rao)多(duo)等(deng)施工(gong)(gong)(gong)(gong)難(nan)點,他們知難(nan)而上(shang),周密計(ji)劃,嚴(yan)格管控,不斷調整部(bu)署。為(wei)加快(kuai)(kuai)施工(gong)(gong)(gong)(gong)進度(du),項(xiang)目部(bu)采(cai)取了有效措施,分工(gong)(gong)(gong)(gong)明確,責任到人,層層落實,層層到位,工(gong)(gong)(gong)(gong)序(xu)銜接緊湊(cou),并針(zhen)對不良(liang)地質段,采(cai)取短進尺、弱爆破(po)、多(duo)循環等(deng)施工(gong)(gong)(gong)(gong)手段,積極(ji)拼搶工(gong)(gong)(gong)(gong)期,生(sheng)產形勢始終保持良(liang)好(hao)的(de)態勢。今年(nian)四季度(du),項(xiang)目部(bu)在工(gong)(gong)(gong)(gong)地掀起大干高(gao)潮,使施工(gong)(gong)(gong)(gong)速度(du)不斷加快(kuai)(kuai),達到“一天一個(ge)模樣”。
施工中,中國水電一局的建設者加強現場安全管理,對施工質量進行嚴格控制,使施工的安全、質量整體處于受控狀態,創造了安全、質量無事故的好成績,泄洪洞工程比原計劃工期提前一個33天實現貫通。