文章(zhang)來源(yuan):國家(jia)電網(wang)公(gong)司 發(fa)布時間:2013-05-30
5月23日15時,三峽電站右岸地下電站27號機組順利完成72小時帶負荷連續試運行。至此,三峽電站32臺機組全部投產發電,三峽工程已圓滿實現2250萬千瓦的設計發電能力。
隨著三峽電站32臺機組全部投產發電,華中電網調整調度方式,積極接納水電。近期,華中區域發生了多次大范圍降雨,特別是四川、重慶、湖北、湖南、江西各流域及三峽水庫來水較大。為此,華中電網一周內調停火電機組容量達551萬千瓦,目前湖北、湖南、江西、四川、重慶火電開機基本已達最小方式。
面(mian)對近期三(san)峽(xia)電(dian)(dian)(dian)(dian)站附近輸電(dian)(dian)(dian)(dian)線路(lu)檢(jian)修多(duo)、水電(dian)(dian)(dian)(dian)大發并(bing)且電(dian)(dian)(dian)(dian)網(wang)火電(dian)(dian)(dian)(dian)開機(ji)基本已(yi)達(da)最小等多(duo)重困難,在國家電(dian)(dian)(dian)(dian)力調度控制中心統籌協調下,國家電(dian)(dian)(dian)(dian)網(wang)公司華中分部和湖北省電(dian)(dian)(dian)(dian)力公司積極配合,確保(bao)27號機(ji)組按計(ji)劃進入(ru)并(bing)網(wang)調試(shi),并(bing)順利完成72小時試(shi)運行。