文(wen)章來源:國家(jia)電網公司 發布時間:2010-12-15
12月14日(ri),向(xiang)家(jia)壩(ba)—上海±800千伏特高(gao)(gao)壓直流輸電(dian)示范(fan)工程啟(qi)動(dong)驗收委(wei)員會(hui)第(di)三(san)次會(hui)議在北(bei)京召(zhao)開。會(hui)議動(dong)員各方堅定信心,明(ming)確(que)目(mu)標(biao),落(luo)實(shi)責任,確(que)保(bao)高(gao)(gao)標(biao)準、高(gao)(gao)質量、高(gao)(gao)效(xiao)率完成設(she)備安裝、竣工驗收和啟(qi)動(dong)調試工作,確(que)保(bao)年(nian)底前(qian)實(shi)現800千伏直流設(she)備和線路帶(dai)電(dian)目(mu)標(biao)。國家(jia)電(dian)網公司(si)總經(jing)理、黨(dang)組書記劉(liu)振亞出(chu)(chu)席(xi)會(hui)議并(bing)作重(zhong)要講話。國家(jia)電(dian)網公司(si)副總經(jing)理、黨(dang)組成員鄭寶森、舒印(yin)彪、欒軍出(chu)(chu)席(xi)會(hui)議。
會議總結(jie)了(le)前一階(jie)段(duan)工(gong)程建設(she)、質量監督檢查、生產(chan)準備(bei)等方面的工(gong)作,審定了(le)奉賢站極Ⅰ系(xi)統和直流線(xian)路(lu)帶(dai)電工(gong)作計劃(hua),部署了(le)工(gong)程下一階(jie)段(duan)的啟動(dong)調試工(gong)作。
目前,向—上(shang)工(gong)(gong)程全線共28個標段的運(yun)行全檢、竣工(gong)(gong)預驗(yan)收(shou)、單項工(gong)(gong)程分省(sheng)驗(yan)收(shou)及投運(yun)前的質(zhi)量(liang)監督檢查工(gong)(gong)作全面完成(cheng);線路本體消缺工(gong)(gong)作結束(shu),工(gong)(gong)程質(zhi)量(liang)優良,符合設計和(he)(he)規范要求(qiu)。奉賢換流(liu)站500千伏交流(liu)系統和(he)(he)極Ⅰ400千伏直流(liu)系統按要求(qiu)完成(cheng)全部施工(gong)(gong)、分系統調試和(he)(he)竣工(gong)(gong)驗(yan)收(shou),具(ju)備了帶(dai)電(dian)條件。
劉(liu)振亞肯(ken)定了向—上工程(cheng)建設成績,并從我國能源發展格局的(de)(de)戰略高度,進(jin)一(yi)步強(qiang)調了推進(jin)工程(cheng)建設的(de)(de)重大意(yi)義。他說,向—上工程(cheng)是(shi)創新工程(cheng)、能源工程(cheng)、環(huan)保(bao)工程(cheng),邁進(jin)的(de)(de)每(mei)一(yi)步、經歷(li)的(de)(de)每(mei)一(yi)天都具有歷(li)史性。
劉(liu)振亞強調(diao),我國水(shui)電(dian)、風(feng)電(dian)等清潔能(neng)(neng)源(yuan)大(da)規模快速發(fa)展,能(neng)(neng)源(yuan)格局正(zheng)在(zai)發(fa)生重(zhong)大(da)而深(shen)刻的變(bian)化。加快特高壓直(zhi)流工(gong)程(cheng)建設和發(fa)展,將西(xi)南大(da)型水(shui)電(dian)基地(di)、西(xi)北大(da)型煤電(dian)和風(feng)電(dian)基地(di)的電(dian)能(neng)(neng)直(zhi)接送至東部負荷中心,對于盡快形成“強交強直(zhi)”的特高壓骨干(gan)網架(jia),大(da)幅提(ti)升電(dian)網優化配置資源(yuan)能(neng)(neng)力(li)和安(an)全穩定運行水(shui)平,以及引(yin)導整個(ge)電(dian)力(li)行業(ye)健康發(fa)展,都具有十分重(zhong)要的意義。
當前,向—上工(gong)(gong)(gong)程(cheng)建(jian)設(she)(she)進入關鍵(jian)階段,工(gong)(gong)(gong)程(cheng)設(she)(she)備到貨時間密集,施工(gong)(gong)(gong)作(zuo)(zuo)業(ye)相互交(jiao)叉,冬(dong)季施工(gong)(gong)(gong)條件惡劣(lie),設(she)(she)備安裝工(gong)(gong)(gong)藝和試驗技術要(yao)求(qiu)極高,系統(tong)調(diao)試方案復雜。劉振亞要(yao)求(qiu)工(gong)(gong)(gong)程(cheng)建(jian)設(she)(she)相關各方進一步提高思想認(ren)識,以科學(xue)嚴謹的(de)(de)作(zuo)(zuo)風和求(qiu)真務實的(de)(de)態度(du)(du),全(quan)力以赴、再(zai)接再(zai)厲,切(qie)實加強工(gong)(gong)(gong)程(cheng)建(jian)設(she)(she)的(de)(de)組織工(gong)(gong)(gong)作(zuo)(zuo),抓好工(gong)(gong)(gong)作(zuo)(zuo)重點(dian)和關鍵(jian)環節,全(quan)面做(zuo)好設(she)(she)備安裝、竣工(gong)(gong)(gong)驗收和系統(tong)調(diao)試等工(gong)(gong)(gong)作(zuo)(zuo),確保(bao)工(gong)(gong)(gong)程(cheng)建(jian)設(she)(she)質(zhi)量、進度(du)(du)和施工(gong)(gong)(gong)安全(quan),并通過工(gong)(gong)(gong)程(cheng)建(jian)設(she)(she)創新技術、培養人才(cai)。
向—上工程沿線網省公司、總部各(ge)部門(men)及相關直屬單位,中國電力工程顧問集團公司、部分電力設計院及試驗院的代表參加會(hui)議。