中國石油西氣東輸二線西段主體焊接突破1000公里

文(wen)章來源:中國石油天然(ran)氣集團公司  發布(bu)時間:2009-10-22

  截至10月(yue)20日,全長1573公里(li)的西氣東輸(shu)二線西段主體(ti)焊(han)接(jie)已完成1024公里(li),突破(po)1000公里(li)大關,焊(han)接(jie)一次合格(ge)率(lv)達98.87%,工程建(jian)設綜合進(jin)度按照計劃運行(xing)。霍(huo)爾果斯首(shou)站、紅柳壓氣站和控制性工程果子(zi)溝隧道群建(jian)設全面(mian)加快推進(jin)。

  西(xi)二線(xian)西(xi)段自2月22日(ri)開工(gong)以來,管(guan)道建(jian)(jian)設(she)(she)(she)項目(mu)經理(li)部(bu)加強組織領(ling)導,科學(xue)調(diao)配施(shi)(shi)工(gong)資源,合理(li)安(an)排施(shi)(shi)工(gong)計劃(hua),抓綜合進(jin)度(du)(du)(du)(du)平(ping)衡。在(zai)(zai)剛剛過去的(de)夏季管(guan)道建(jian)(jian)設(she)(she)(she)黃金期(qi),掀起管(guan)道建(jian)(jian)設(she)(she)(she)高(gao)潮,在(zai)(zai)資源調(diao)配上(shang),強調(diao)統籌(chou)考慮,確(que)保(bao)(bao)重(zhong)點,集中優勢裝備,在(zai)(zai)西(xi)段展開大兵團(tuan)機械化流水(shui)作(zuo)業,為后期(qi)建(jian)(jian)設(she)(she)(she)贏得時(shi)間(jian)。結合管(guan)材(cai)供應(ying)情況,在(zai)(zai)重(zhong)點加快新(xin)疆段建(jian)(jian)設(she)(she)(she)的(de)同(tong)(tong)時(shi),推進(jin)甘肅段和(he)寧陜段的(de)施(shi)(shi)工(gong)綜合進(jin)度(du)(du)(du)(du)。EPC總承(cheng)包在(zai)(zai)確(que)保(bao)(bao)工(gong)程進(jin)度(du)(du)(du)(du)的(de)同(tong)(tong)時(shi),充分發(fa)揮(hui)專業化管(guan)理(li)優勢,加強安(an)全質(zhi)量(liang)(liang)管(guan)理(li),強化巡檢(jian)(jian)、飛檢(jian)(jian)、抽(chou)檢(jian)(jian)制(zhi)度(du)(du)(du)(du),對重(zhong)要工(gong)序(xu)實施(shi)(shi)現場監控,建(jian)(jian)立施(shi)(shi)工(gong)承(cheng)包商質(zhi)量(liang)(liang)保(bao)(bao)證(zheng)體系,實行安(an)全質(zhi)量(liang)(liang)績效考核一票否決制(zhi)度(du)(du)(du)(du),確(que)保(bao)(bao)工(gong)程建(jian)(jian)設(she)(she)(she)質(zhi)量(liang)(liang)始終保(bao)(bao)持在(zai)(zai)98.5%以上(shang)。監理(li)工(gong)作(zuo)著力加大監理(li)巡視和(he)檢(jian)(jian)查力度(du)(du)(du)(du),制(zhi)定相(xiang)應(ying)的(de)糾正和(he)預防(fang)措施(shi)(shi),保(bao)(bao)證(zheng)施(shi)(shi)工(gong)質(zhi)量(liang)(liang)處于(yu)受控狀(zhuang)態。

  在各參建單位的共(gong)同努力下,各項工(gong)(gong)(gong)(gong)作全面推進(jin)。工(gong)(gong)(gong)(gong)程(cheng)進(jin)度報表顯示,截(jie)至(zhi)目前,全線(xian)已完(wan)成(cheng)(cheng)8.3391萬(wan)道(dao)補(bu)口(kou)任務,二次回(hui)填(tian)完(wan)成(cheng)(cheng)715公里。霍爾果斯首站、紅柳壓(ya)氣(qi)站壓(ya)縮機區基礎完(wan)成(cheng)(cheng)混凝土(tu)澆筑(zhu),其余20座站場已有(you)11座進(jin)行單體土(tu)建施工(gong)(gong)(gong)(gong)。154處(chu)三穿工(gong)(gong)(gong)(gong)程(cheng)已開工(gong)(gong)(gong)(gong)42處(chu)。果子溝隧(sui)道(dao)群中,4A號隧(sui)道(dao)已于(yu)10月(yue)5日貫通(tong),寧夏段(duan)冰溝和上河沿(yan)隧(sui)道(dao)于(yu)9月(yue)中旬貫通(tong)。施工(gong)(gong)(gong)(gong)難(nan)度最大、全長3088米的1號隧(sui)道(dao)累(lei)計進(jin)尺1934米,2到6號隧(sui)道(dao)累(lei)計完(wan)成(cheng)(cheng)2203米。

  值得(de)一提的(de)是,由中國石油管道三公司(si)承(cheng)建的(de)石河子段(duan)施工(gong)中,員(yuan)(yuan)工(gong)們愛護一草一木,珍惜一禾一苗(miao),作業帶嚴格(ge)控制在28米之(zhi)內,盡(jin)量(liang)減少果樹移栽與砍伐。施工(gong)機組(zu)印制了服務卡,購買了澆水的(de)管子,隨時滿(man)足村(cun)民用水需要。村(cun)民也主動給施工(gong)人員(yuan)(yuan)送水果慰問,營造(zao)了互相配合,共創(chuang)和諧的(de)良好氛圍,保證了管道主體焊接于9月17日提前完工(gong),得(de)到了新疆維(wei)吾爾自治區(qu)領導(dao)的(de)高度評價。