文章來源:國家電網公司(si) 發布時間:2016-07-06
7月1日,從國網(wang)河北(bei)省電力公司(si)傳(chuan)來(lai)消(xiao)息,錫盟—山東(dong)工(gong)程(cheng)線(xian)(xian)路(lu)工(gong)程(cheng)(河北(bei)段(duan))順利(li)通過(guo)電力質(zhi)量監督總(zong)站導(dao)地線(xian)(xian)架(jia)(jia)設前階段(duan)質(zhi)量監檢,全(quan)線(xian)(xian)率先完成(cheng)架(jia)(jia)線(xian)(xian)轉序,該工(gong)程(cheng)建(jian)設即將全(quan)面進入架(jia)(jia)線(xian)(xian)施工(gong)階段(duan)。
“這標志著公司在錫盟—山東工程建設管(guan)理(li)中(zhong)(zhong),繼全線率先(xian)組塔后,較里程碑(bei)計劃提前3個月完成架線轉序,從而(er)再次在沿線4個省(sheng)公司中(zhong)(zhong)進度領先(xian),成功(gong)創造(zao)了工程施工新速度。”國(guo)網河北電力(li)特(te)高壓指揮(hui)部相關負責人介紹說(shuo)。
據(ju)了解,本次質量(liang)監(jian)督檢(jian)查組嚴格按照驗(yan)收(shou)(shou)流程(cheng),對現(xian)場鐵(tie)塔(ta)外(wai)觀、螺(luo)栓緊固、鐵(tie)塔(ta)傾斜等指標進行(xing)嚴格測量(liang)與檢(jian)查,并詳細檢(jian)查了各項報(bao)審資(zi)料(liao)(liao)、鐵(tie)塔(ta)組立評級記錄(lu)(lu)、鐵(tie)塔(ta)開(kai)箱檢(jian)查記錄(lu)(lu)、三級自檢(jian)記錄(lu)(lu)等資(zi)料(liao)(liao)。通(tong)過(guo)檢(jian)查,驗(yan)收(shou)(shou)組專家們認為該標段(duan)工程(cheng)實體及各段(duan)數(shu)據(ju)均符合設(she)計(ji)要求,工程(cheng)整體質量(liang)優良,檔案資(zi)料(liao)(liao)齊(qi)全,達到(dao)規程(cheng)規范驗(yan)收(shou)(shou)標準,具備(bei)導地線架設(she)實施條(tiao)件,同意(yi)轉(zhuan)序(xu)。
為順利實現(xian)工(gong)程(cheng)轉序,各參建單(dan)(dan)位(wei)抽調精干力量,在(zai)確(que)(que)保工(gong)程(cheng)建設安(an)全(quan)、質(zhi)量和(he)工(gong)藝(yi)的(de)前提下,超(chao)前策劃(hua)(hua),周密(mi)組(zu)織(zhi),不斷加快施(shi)工(gong)進(jin)度。施(shi)工(gong)單(dan)(dan)位(wei)積極開(kai)展“三(san)級檢查驗(yan)收”,編制(zhi)架(jia)線(xian)(xian)施(shi)工(gong)方案,組(zu)織(zhi)落實架(jia)線(xian)(xian)施(shi)工(gong)人(ren)員、機械、設備,并于6月25日順利通過機具(ju)安(an)全(quan)性第三(san)方評(ping)價;監理單(dan)(dan)位(wei)認(ren)真組(zu)織(zhi)初檢,對方案提出(chu)審(shen)查意(yi)見(jian),組(zu)織(zhi)架(jia)線(xian)(xian)物資開(kai)箱驗(yan)收;業(ye)主(zhu)項目部統籌策劃(hua)(hua),落實架(jia)線(xian)(xian)物資到貨(huo),組(zu)織(zhi)電氣施(shi)工(gong)圖紙交(jiao)(jiao)付(fu)及交(jiao)(jiao)底(di),借助(zhu)公司優勢資源,組(zu)織(zhi)檢修公司超(chao)前介入,嚴格進(jin)行導(dao)地(di)線(xian)(xian)架(jia)設前階段中間驗(yan)收,嚴把工(gong)程(cheng)質(zhi)量關,確(que)(que)保工(gong)程(cheng)本體質(zhi)量可控、在(zai)控,達(da)到了工(gong)程(cheng)建設安(an)全(quan)高效的(de)目的(de)。
“工(gong)(gong)程(cheng)(cheng)計(ji)劃(hua)今年(nian)(nian)7月(yue)初轉(zhuan)入架線(xian)施(shi)工(gong)(gong),年(nian)(nian)底(di)前(qian)實現工(gong)(gong)程(cheng)(cheng)主體竣(jun)工(gong)(gong),將為后續“兩交三直”工(gong)(gong)程(cheng)(cheng)建設(she)積累經(jing)驗,起到良好(hao)的示范作用。”該負責人(ren)表示。下一(yi)步,各參建單(dan)位將按照建設(she)世界一(yi)流電網的要求,強化人(ren)員培訓、加強工(gong)(gong)作策劃(hua)、嚴格(ge)過程(cheng)(cheng)管(guan)控(kong),確保工(gong)(gong)程(cheng)(cheng)質量始終(zhong)處于受控(kong)狀態,全(quan)力(li)打(da)造“安全(quan)可靠、自主創新、經(jing)濟合理、環境友好(hao)、國際一(yi)流”的優質精(jing)品工(gong)(gong)程(cheng)(cheng)。